Skip to main content

Progress

On time
  • Not yet begun
  • In progress
  • Completed

Official description

Perform an audit of the Town's irrigation system.
(According to the action plan)

Description

In July 2022, the Town worked with Northern Water to complete audits at Children's Park, Little Sagamore Park, and Big Sagamore Park. These audits happened post-Marshall Fire and were designed to support the recovery process in a water-wise way. The Town also worked with Aqua Engineering to complete a full irrigation assessment and audit at Community Park in August of 2022.

status last confirmed: July 2024

Summary and contacts

  • H2O Use Reduction Potential

    Marginally reduces
  • Cost

Information updated 07/18/2024